In a report on the funding performance of the oil firm from January to December 202, the Nigerian National Petroleum Company Limited disclosed that it has spent N100 billion on the refineries’ rehabilitation in 2021 and the funds were pumped into revamping the facilities on a monthly basis.
Although, no refinery was mentioned in the report, Nigeria’s refineries had been under the management of NNPC, as the rehabilitation of one of the facilities, Port Harcourt Refining Company, had been ongoing.
The other refineries under the NNPC’s management include the Kaduna Refining and Petrochemical Company, as well as the Warri Refining and Petrochemical Company.
In the NNPC’s latest funding performance report, the firm stated that N8.33bn was spent monthly for a period of 12 months beginning from January to December 2021 on refinery rehabilitation.
READ ALSO: IMF Advised Nigeria, Others to Prepare for Turbulence in Financial Markets
The Federal Government has been making moves to get the country’s refineries back on stream, as Nigeria currently imports bulk of its refined petroleum products, which has resulted in humongous subsidy spendings by the NNPC, the sole importer of petrol into Nigeria for more than four years and counting.
The Federal Executive Council approved the contract for the EPCIC of the Port Harcourt refinery on March 17, 2021, and work on the facility commenced last year.
The council approved the award of the PHRC EPCIC contract to Tecnimont in March, and the contract agreement was signed on April 6, 2021, as the report seen in Abuja on Friday indicated that additional funds had been processed to ensure the continued rehabilitation of the plant.
In August last year, the Federal Executive Council approved the sum of $1.48bn for the rehabilitation of both Warri and Kaduna refineries.
The Minister of State for Petroleum Resources, Chief Timipre Sylva, announced this at the end of one of the weekly FEC meetings held in Abuja.
Sylva had explained that the rehabilitation of Warri and Kaduna refineries would be awarded to Messers Saipem SPA and Saipem Contracting Limited at the combined total sum of $1.484bn and would be rehabilitated in three phases of 21, 23 and 33 months.